Rescheduling of Background JObs

$
0
0

Hi,

 

We are moving Production system to new hardware.

 

We have set Backgound process=0 and started SAP system on new hardware.

 

We have suspended jobs by report BTCTRNS1 and changed Backgound process=6.

 

Now we want to release jobs by report  BTCTRNS2.

 

Now questions is

 

Before we release jobs by report  BTCTRNS2. what care should we take?

 

Any thing we should confirm from customer because customer might have some jobs which they might want to reschedule?

so should we just go ahead and release backgound jobs?

 

Regards,

Vinay